AngloGold Ashanti has said production guidance for 2016 is estimated to be between 3.6Moz to 3.8Moz.
It said total cash costs are estimated to be between $680/oz and $720/oz and all-in sustaining costs between $900/oz and $960/oz at average exchange rates against the US dollar of 15.00 (Rand), 4.00 (Brazil Real), 0.70 (Aus $) and 14.90 (Argentina Peso), with oil at $35/bl average for the year.
The miner said capital expenditure is anticipated to be between $790m and $850m, of which $120m to $140m is earmarked for projects.
Corporate and marketing costs are estimated to be between $75m and $90m and expensed exploration and study costs including equity accounted investments at $130m to $150m.
Depreciation and amortisation is forecast at $820m and interest and finance costs are expected to be $190m and $175m.